Earned value management(EVM) integrates the scope baseline with the ()baseline

2021-11-09 16:46:23 薄心之心 2019

Earned value management(EVM) integrates the scope baseline with the ()baseline,along with schedule baseline,to form the performance baseline,which helps the project management team assess and measure project performance and progress.

A、qulity

B、risk

C、change

D、cost

参考答案:D

参考解析:挣值管理(EVM)将范围基线与()基线结合起来,并与进度基线一起构成绩效基线,这有助于项目管理团队评估和衡量项目的绩效和进度。

A、质量

B、风险

C、变化

D、成本

—— 完 ——
  • Unity打包时提示错误:The type or namespace name ‘MenuItemAttribute‘ could not be found
  • ()is not included in the main contents of the operation and maintenance of the  information system.
  • Vue中<style scoped lang=“less“> 说明
  • 采购管理系统(PMS-Purchase Management System)
  • C#图像处理之边缘检测(Smoothed)的方法
  • Unity3D:解决VS断点Could not insert breakpoint ‘xxx’: The breakpoint could not be bound问题
  • 蘑菇管理定律(Mushroom Management)
  • Vue引入ElementUI错误:This dependency was not found: * element-ui/lib/theme-chalk/index.css in ./src/main.js
  • mysql数据库error: Found option without preceding group in config file 问题
  • The organization shall undertake root cause analysis and determine potential actions to prevent the occurrence or recurrence of()

© CopyRight 2014~2024 薄学网.